Regarding decoupling from Russia-controlled electricity system in February 2025
Comunicato Precedente
Comunicato Successivo
The TSOs of Estonia, Latvia, and Lithuania have sent a notice of non-extension of the agreement on parallel energy system operation – so called BRELL agreement, which has been defining the terms of operation of the Baltic countries in the Russia-controlled electricity system IPS/UPS.
According to the notice, the agreement will expire on the 7th of February 2025. On the 8th of February, the Baltic TSOs will disconnect Estonian, Latvian, and Lithuanian electricity systems from IPS/UPS and will start a joint isolated operation test.
The synchronisation of the Baltic electricity systems with the Continental Europe Synchronous Area is planned on the 9th of February 2025.