Regarding decoupling from Russia-controlled electricity system in February 2025

The TSOs of Estonia, Latvia, and Lithuania have sent a notice of non-extension of the agreement on parallel energy system operation – so called BRELL agreement, which has been defining the terms of operation of the Baltic countries in the Russia-controlled electricity system IPS/UPS. According to the notice, the agreement will expire on the 7 thof February 2025. On the 8 thof February, the Baltic TSOs will disconnect Estonian, Latvian, and Lithuanian electricity systems from IPS/UPS...
Comunicato Precedente

next
Comunicato Successivo

next
LITGRID AB, (informazione.it - comunicati stampa - energia)

The TSOs of Estonia, Latvia, and Lithuania have sent a notice of non-extension of the agreement on parallel energy system operation – so called BRELL agreement, which has been defining the terms of operation of the Baltic countries in the Russia-controlled electricity system IPS/UPS.

According to the notice, the agreement will expire on the 7th of February 2025. On the 8th of February, the Baltic TSOs will disconnect Estonian, Latvian, and Lithuanian electricity systems from IPS/UPS and will start a joint isolated operation test.

The synchronisation of the Baltic electricity systems with the Continental Europe Synchronous Area is planned on the 9th of February 2025.

The individual authorized by LITGRID AB to provide additional information:
Jurga Eivaitė
Communications project manager
phone: +370 613 19977, e-mail: [email protected]  


Per maggiori informazioni
Sito Web
litgrid.eu
Ufficio Stampa
 Nasdaq GlobeNewswire (Leggi tutti i comunicati)
2321 Rosecrans Avenue. Suite 2200
90245 El Segundo Stati Uniti
Allegati
Slide ShowSlide Show
Non disponibili